Hyderabad: The Hyderabad High Court has strongly criticized the Hyderabad Metropolitan Development Authority (HMDA) over its handling of construction permits. The court highlighted a pattern of inconsistent decision-making and suggested a “biased” application of rules in the approval process. This criticism arose during a hearing of a contempt petition filed by Akshaya Developers, who claimed that their application for construction permits was unjustly rejected by HMDA, while other applicants received approval for similar projects.

High Court Criticizes HMDAs Actions

Unequal Treatment of Applicants

During the hearing, Justice T. Vinod Kumar pointed out the unequal treatment faced by different applicants seeking construction permits from HMDA. He emphasized the discrepancies in HMDA’s approach, questioning why some applications were approved while others, like that of Akshaya Developers, were denied. The inconsistency in the approval process for HMDA construction permits raised concerns about transparency and fairness in the authority’s decision-making.

Akshaya Developers vs. Ganapati Sachidananda Avadhuta Peetham Trust

Akshaya Developers, the petitioner in the case, argued that their request for construction permits was denied due to a lack of a service road. However, a similar permit was granted to another organization, the Ganapati Sachidananda Avadhuta Peetham Trust, for construction in the same area. This discrepancy in granting HMDA construction permits to different entities led to questions regarding the rationale behind the authority’s decisions. The denial based on technical grounds, despite allowing other projects with similar issues, pointed to potential favoritism.

Concerns Over Technical Grounds for Denial

Justice Vinod Kumar further questioned HMDA’s basis for rejecting Akshaya Developers’ application on technical grounds, especially given that many other buildings lacking proper road access have previously been granted HMDA construction permits. The judge’s observations highlighted a possible inconsistency in how HMDA applies its criteria, leading to a perceived lack of fairness and impartiality. This issue has put a spotlight on the broader processes involved in granting construction permits in Hyderabad.

HMDA’s Non-Compliance with Court Orders

Despite the High Court dismissing appeals filed by HMDA on September 10, the authority has not acted on the directives regarding Akshaya Developers’ permit application. The judge interpreted HMDA’s inaction as a deliberate violation of the court’s orders, further complicating the legal dispute. The apparent disregard for the court’s instructions has added to the criticism of HMDA’s handling of construction permits, suggesting a need for greater accountability.

Court Summons HMDA Officials for Explanations

In light of these developments, the Hyderabad High Court has summoned HMDA Commissioner Sarfaraz Ahmed and Planning Director A. Vidyadhar to provide personal explanations for their failure to comply with court orders. The court’s directive underscores the seriousness of the allegations against HMDA and reflects the judiciary’s demand for transparency in how HMDA construction permits are managed. This move may pave the way for more rigorous oversight of the authority’s actions in the future.

Implications for Construction Permit Approvals in Hyderabad

The ongoing controversy surrounding HMDA’s approval process has broader implications for the construction industry in Hyderabad. The issues raised in the case of Akshaya Developers highlight the need for uniformity and fairness in the issuance of HMDA construction permits. The court’s intervention may push the authority to review its procedures and ensure that all applicants are treated equitably. As the legal proceedings unfold, developers and stakeholders are closely monitoring how HMDA addresses these criticisms and whether it will take steps to rectify its approach.

Conclusion: A Call for Fair Practices

The Hyderabad High Court’s criticism of HMDA has brought to light the importance of fair practices in the approval of HMDA construction permits. The allegations of unequal treatment have raised serious concerns among developers and have prompted a judicial review of the authority’s methods. As HMDA officials prepare to respond to the court’s summons, the outcome could have a lasting impact on how construction permits are granted in Hyderabad, emphasizing the need for transparency and consistency in the process.

Disclaimer: This content is intended for informational purposes and provides an overview of the legal dispute between the Hyderabad High Court and the Hyderabad Metropolitan Development Authority (HMDA) regarding construction permit approvals. It does not take a stance for or against any party involved in the proceedings. Readers are encouraged to consult official sources for accurate legal interpretations.